In the weekend I made some changes in the
materials.
It was little changes(adding one more layer) in
some ceilings and floors..
The program ran but stopped in several days of
March with the problem out of bonds again.
I also correct the tilt problem but it didn´t
matter.The problem continues.
Now I have an almost error free program(I have
errors because I didn´t model the Hvac system ans the out of bonds) which
stops in particulary days.
The strange thing is if you ran the simulation for
March for those days between the error days you get results in the some order of
the previous and following month.
Now I even don´t know if the results from
January to March and from April to December are correct.Are the results the
program gives me possible and correct, a little lower or a little
higher?
Best regards
Lourenço
To unsubscribe from this group, send an email to: EnergyPlus_Support-unsubscribe@xxxxxxxxxxxxxxx The primary EnergyPlus web site is found at: http://www.energyplus.gov The group web site is: http://groups.yahoo.com/group/EnergyPlus_Support/ Your use of Yahoo! Groups is subject to the Yahoo! Terms of Service. |
Attachment not found: D:\Documents_And_Settings\L-Lawrie\Eudora\Attach\12-11-021.zip