[EnergyPlus_Support] design load output questions
Hi
I wonder if someone can help me interpret some of the E+ output. I'm
trying to do some design sizing. From one run, I have:
a) file.CSV - Z1 RADIANT PANEL:Hydronic Low Temp Radiant Cooling Rate
[W](Hourly) = 4161.89 W (autosized)
b) file.CSV - ZN1:E PERIM SPC:Zone/Sys Sensible Cooling Rate[W]
(Hourly) = 8105.6 (fixed 6 ACH)
c) file.EIO - DesLoad {W} Cooling = 10277.00 W
d) file.ZSZ - ZN1:E PERIM SPC:VANC_INTL CLG .4% DB=>MWB:Des Cool
Load [W] = 11587.44 W
my two questions are:
1. should c and d be the same? or, why not?
2. should (a + b + latent) = c or d?
Thanks
Shaun Martin
------------------------ Yahoo! Groups Sponsor --------------------~-->
Make a clean sweep of pop-up ads. Yahoo! Companion Toolbar.
Now with Pop-Up Blocker. Get it for free!
http://us.click.yahoo.com/L5YrjA/eSIIAA/yQLSAA/dkFolB/TM
--------------------------------------------------------------------~->
The primary EnergyPlus web site is found at:
http://www.energyplus.gov
The group web site is:
http://groups.yahoo.com/group/EnergyPlus_Support/
Attachments are not allowed -- please post any files to the appropriate folder in the Files area of the Support Web Site.
Yahoo! Groups Links
<*> To visit your group on the web, go to:
http://groups.yahoo.com/group/EnergyPlus_Support/
<*> To unsubscribe from this group, send an email to:
EnergyPlus_Support-unsubscribe@xxxxxxxxxxxxxxx
<*> Your use of Yahoo! Groups is subject to:
http://docs.yahoo.com/info/terms/