[EnergyPlus_Support] Re: Why the generators stop working when selected "Follow Thermal"
- To: EnergyPlus_Support@xxxxxxxxxxxxxxx
- Subject: [EnergyPlus_Support] Re: Why the generators stop working when selected "Follow Thermal"
- From: "pzhaocsm" <pzhaocsm@xxxxxxxxx>
- Date: Thu, 10 Jun 2010 17:09:33 -0000
- Delivered-to: mailing list EnergyPlus_Support@xxxxxxxxxxxxxxx
- Delivery-date: Thu, 10 Jun 2010 11:09:51 -0600
- Dkim-signature: v=1; a=rsa-sha256; c=relaxed/relaxed; d=yahoogroups.com; s=lima; t=1276189790; bh=RQlBFXIoafYT3reCmBeBr1nZ9gKu2PGbd7bqPcho7G8=; h=Received:Received:X-Yahoo-Newman-Id:X-Sender:X-Apparently-To:X-Received:X-Received:X-Received:X-Received:X-Received:To:Message-ID:User-Agent:X-Mailer:X-Originating-IP:X-eGroups-Msg-Info:X-Yahoo-Post-IP:From:X-Yahoo-Profile:Sender:MIME-Version:Mailing-List:Delivered-To:List-Id:Precedence:List-Unsubscribe:Date:Subject:Reply-To:X-Yahoo-Newman-Property:Content-Type:Content-Transfer-Encoding; b=oig/i4wNertvF/Mqkw6vkqBO0VC7sEbX7ldWLEuz54rseGv3fqqAeOsUrVBTThQqQTfVq+Oln5rNNvvu6hiCrgld8vZVSduOWo6PLnelVwLh5IXrw9UxT8bCkN5QGpex
- Domainkey-signature: a=rsa-sha1; q=dns; c=nofws; s=lima; d=yahoogroups.com; b=O8iICsTKzQNeiMpB15WpE/9QhH7DX/j2mZc14WqUIC3o0jkyUeNSugMuQzNswGj+G/7zTpBOt3gF7Fw2u8dAGJAXTwM1HVY+FrIajDmfL9V2XgUmTR1Sv25lZupGzqrT;
- Envelope-to: linda@xxxxxxxxxxxxxx
- List-id: <EnergyPlus_Support.yahoogroups.com>
- List-unsubscribe: <mailto:EnergyPlus_Support-unsubscribe@yahoogroups.com>
- Mailing-list: list EnergyPlus_Support@xxxxxxxxxxxxxxx; contact EnergyPlus_Support-owner@xxxxxxxxxxxxxxx
- Reply-to: EnergyPlus_Support@xxxxxxxxxxxxxxx
- Sender: EnergyPlus_Support@xxxxxxxxxxxxxxx
- User-agent: eGroups-EW/0.82
Hello Brent,
Thank you very much for your reply! I really appreciate it! I have tried the MicroCoGeneration.idf already, and I got some problem. As I asked in message # 17081. I reproduce the question and paste here:
Thanks a lot again!
Hello,
I have tried the MicroCoGeneration.idf file. The MicroCHP unit is currently providing around 50% of the total heating load (generator operation scheme: follow thermal), but I want the MicroCHP unit provide 100% heating load. Because the Generator:MicroCHP is not normalized, I can not simply increase its capacity from current 5kW to 10kW, so I added another MicroCHP unit working parallel with the first one. But the simulation result is: the total thermal output of
the two MicroCHP units is still 50% of the total heating load, both of them are working, but both of their thermal and electric output reduced to 50% rated output, My question is: How can the two MicroCHP units working parallel at their rated output to meet the thermal load?
Thank you very much! I am looking forward to discussing with you.
Best,
Peng
------------------------------------
Primary EnergyPlus support is found at:
http://energyplus.helpserve.com or send a message to energyplus-support@xxxxxxxx
The primary EnergyPlus web site is found at:
http://www.energyplus.gov
The group web site is:
http://groups.yahoo.com/group/EnergyPlus_Support/
Attachments are currently allowed but be mindful that not everyone has a high speed connection. Limit attachments to small files.
EnergyPlus Documentation is searchable. Open EPlusMainMenu.pdf under the Documentation link and press the "search" button.
Yahoo! Groups Links
<*> To visit your group on the web, go to:
http://groups.yahoo.com/group/EnergyPlus_Support/
<*> Your email settings:
Individual Email | Traditional
<*> To change settings online go to:
http://groups.yahoo.com/group/EnergyPlus_Support/join
(Yahoo! ID required)
<*> To change settings via email:
EnergyPlus_Support-digest@xxxxxxxxxxxxxxx
EnergyPlus_Support-fullfeatured@xxxxxxxxxxxxxxx
<*> To unsubscribe from this group, send an email to:
EnergyPlus_Support-unsubscribe@xxxxxxxxxxxxxxx
<*> Your use of Yahoo! Groups is subject to:
http://docs.yahoo.com/info/terms/