[EnergyPlus_Support] Re: Heating/Setpoint Controller



Hi, I am stuck on the same problem. 
Is Energyplus EMS the only way? Or which 4-5 variables can you adjust?
Also, what do you mean by not using VAV? I am using an AHU and VAV or not, there is the same problem, since you have to use a Setpoint manager for the coils.

It is a very common HVAC configuration, which I cannot find how to configure...
Any idea?

Regards,

Germán.

--- In EnergyPlus_Support@xxxxxxxxxxxxxxx, YuanLu Li <yli006@...> wrote:
>
> 
> If yu do not have pre-heat and reheat and there is not need to use VAV, you should not model using VAV.   The zone thermostat should be used to control the cooling and heating coils directly. When you use VAV dampler, the theremostat controls the damper which change the flow rate which results in different zone temperature.    The process is more complex.  You need to adjust four or five variables to work together to make the system work.  ============================In a real VAV system, a computer control system is used to control the fan speed.  Pressure sensors are also required.  Duct temperature, diffuser temperature and room temperature are modified to make the desission on whaat to do.  Dr. Li   
>  To: EnergyPlus_Support@xxxxxxxxxxxxxxx
> From: matthew.sverre.anderson@...
> Date: Thu, 10 Nov 2011 15:13:58 +0000
> Subject: [EnergyPlus_Support] Heating/Setpoint Controller
> 
> 
> 
> 
> 
> 
> 
> 
> 
> 
> 
> 
> 
> 
> 
> 
> 
> 
>  
> 
> 
> 
>   
> 
> 
>     
>       
>       
>       Hello Everybody, I have a question that likely (or at least hopefully!) has an easy answer and I am simply too foolish to know it.
> 
> 
> 
> So I have a building which I modeled as a VAV with no reheat, and no preheat coil. I want the coils to operate as needed and simply ignore any frost warnings. However, I currently have no schedule for either since there will be many times during the fall/spring where we might need to heat/cool during the same day or during the week. 
> 
> 
> 
> The problem I am currently having is that the heating/cooling coils are operating year long at the same time. I want the HC to operate when the building needs heating, the CC to operate when the building needs cooling (neither to operate at the same time). Am I thinking about this incorrectly? 
> 
> 
> 
> Also is there a way to implement a dead band above/below the set point where the system is "satisfied" to prevent the system from "slamming" on/off?
>




------------------------------------

Primary EnergyPlus support is found at:
http://energyplus.helpserve.com or send a message to energyplus-support@xxxxxxxx

The primary EnergyPlus web site is found at:
http://www.energyplus.gov

The group web site is:
http://groups.yahoo.com/group/EnergyPlus_Support/

Attachments are currently allowed but be mindful that not everyone has a high speed connection.  Limit attachments to small files.

EnergyPlus Documentation is searchable.  Open EPlusMainMenu.pdf under the Documentation link and press the "search" button.
Yahoo! Groups Links

<*> To visit your group on the web, go to:
    http://groups.yahoo.com/group/EnergyPlus_Support/

<*> Your email settings:
    Individual Email | Traditional

<*> To change settings online go to:
    http://groups.yahoo.com/group/EnergyPlus_Support/join
    (Yahoo! ID required)

<*> To change settings via email:
    EnergyPlus_Support-digest@xxxxxxxxxxxxxxx 
    EnergyPlus_Support-fullfeatured@xxxxxxxxxxxxxxx

<*> To unsubscribe from this group, send an email to:
    EnergyPlus_Support-unsubscribe@xxxxxxxxxxxxxxx

<*> Your use of Yahoo! Groups is subject to:
    http://docs.yahoo.com/info/terms/