Thanks Sean and Xing for your reply. I have just dampers in my VAV boxes, reheat in some cases. I think I gonna go for combining "design" thermals zones according to loads similarity (perimeter orientation, core, etc)

Best Regards

Ric.


--- In EnergyPlus_Support@xxxxxxxxxxxxxxx, "Jean marais" <jeannieboef@...> wrote:
>
> The answere is: "it depends".
> 
> I have it on pretty good authority (Expert for the EAp2 credit on LEEDuser, if I remember correctly...Christiaan Schaffer?) that energy consumers (like fans) should be explicitly modelled as is in your real design for the design case. If your baseline case VAV box has a local integrated fan then I would say you must model each one and the same goes for fancoils. For big repetitions look into using the eplus macro functionallity. As for thermal zoning, eplus can sometimes not apply multipliers to equipment, but can to zones. You could divide a large open floor into a multipliable zone with VAV and its portion of lighting, persons and other loads and simply apply a zone multiplier. Just take care to adjust the sizing (auto sizing) of the plant and airloop systems appropriately.
> 
> If your VAV terminal box is just a damper, then sure, zone division as you described will do. Keep in mind the 15ft rule for the depth of the zone. And I believe you must use real room divisions in your zoning if you have planning for them. 
> 
> I've not opened my ASHRAE 90.1 in some time so feel free to correct me.
> 
> 
> --- In EnergyPlus_Support@xxxxxxxxxxxxxxx, Richard Frendior <rfenergymodel@> wrote:
> >
> > Hi,
> >   I'm modelling an office building for 90.1 Apendix G. Im a bit stuck with how much detail I have to model since the building is quite big. Do I need to zone the open plan office by dividing it into zones for each VAV box? Or can I just make one core zone,  4 perimeter zones (one for each orientation), plus one zone for combining unheated spaces (elevators, stairs, etc)?
> > 
> > Thanks
> > 
> > Ric.
> >
>




------------------------------------

Primary EnergyPlus support is found at:
http://energyplus.helpserve.com or send a message to energyplus-support@xxxxxxxx

The primary EnergyPlus web site is found at:
http://www.energyplus.gov

The group web site is:
http://groups.yahoo.com/group/EnergyPlus_Support/

Attachments are currently allowed but be mindful that not everyone has a high speed connection.  Limit attachments to small files.

EnergyPlus Documentation is searchable.  Open EPlusMainMenu.pdf under the Documentation link and press the "search" button.
Yahoo! Groups Links

<*> To visit your group on the web, go to:
    http://groups.yahoo.com/group/EnergyPlus_Support/

<*> Your email settings:
    Individual Email | Traditional

<*> To change settings online go to:
    http://groups.yahoo.com/group/EnergyPlus_Support/join
    (Yahoo! ID required)

<*> To change settings via email:
    EnergyPlus_Support-digest@xxxxxxxxxxxxxxx 
    EnergyPlus_Support-fullfeatured@xxxxxxxxxxxxxxx

<*> To unsubscribe from this group, send an email to:
    EnergyPlus_Support-unsubscribe@xxxxxxxxxxxxxxx

<*> Your use of Yahoo! Groups is subject to:
    http://docs.yahoo.com/info/terms/