RE: [EnergyPlus_Support] Process loads below 25%





Hi Oscar,

This happens to me sometimes, I think, if I remember correctly, it won't change to "Y". As long as you put the exceptional calculation in and provide a narrative as to why your loads are under 25% of baseline cost then the overall form will be accepted. 

Annie


To: EnergyPlus_Support@xxxxxxxxxxxxxxx
From: oscar.buchely@xxxxxxxxxxx
Date: Wed, 6 Jun 2012 22:27:48 +0100
Subject: [EnergyPlus_Support] Process loads below 25%

 

Hello.

I just fill up a LEED format for EAp2. in my model process loads are below 25%. I had all documentation an calculation to support that. but when I fill up the table
EAP2-4 my process loads not meet the requirements of 25% and even though I upload support documentation to show that in section EAP2-9 the compliance is still showing me NO.

I was trying to do it as exceptional calculation measurement but in that section the form only allow to change the proposed case and not the base line.

Any help would be appreciated

Thanks




__._,_.___


Primary EnergyPlus support is found at:
http://energyplus.helpserve.com or send a message to energyplus-support@xxxxxxxx

The primary EnergyPlus web site is found at:
http://www.energyplus.gov

The group web site is:
http://groups.yahoo.com/group/EnergyPlus_Support/

Attachments are currently allowed but be mindful that not everyone has a high speed connection.  Limit attachments to small files.

EnergyPlus Documentation is searchable.  Open EPlusMainMenu.pdf under the Documentation link and press the "search" button.




Your email settings: Individual Email|Traditional
Change settings via the Web (Yahoo! ID required)
Change settings via email: Switch delivery to Daily Digest | Switch to Fully Featured
Visit Your Group | Yahoo! Groups Terms of Use | Unsubscribe

__,_._,___