Harshul,

In addition to Jean’s good suggestion, here are some of my thoughts:

 

o   You might also find that a large or complex model takes 10-20 minutes or longer to run just DesignDays!  If that’s the case, consider making a much smaller “dummy” file with enough zones for testing.  This smaller file should run a lot faster and enable faster debugging.

§  The “dummy” file must follow all of the normal requirements, including correct zone names.

§  Certain multi-zone systems will need “doctoring “ to get the zone / system air balance in line

§  If you are autosizing anything, you may find that, for example, the autosized supply air flow is less than the specified exhaust air flow, causing a system to run at 100% OA continuously.  (Supply air flow is small because your “dummy” file represents a smaller building with less load.)

o   These might also be helpful (but are not tested yet) for models that take a long time to run, even when using the above suggestions:

§  Set Building, Solar Distribution to “MinimalShadowing”

§  Set ShadowCalculation, Calculation Frequency to a larger value than default (say, 30 days)

§  Set Timestep to 2 (maybe even 1.  Accuracy is reduced, but this should help for speed until you are confident that all problems are resolved.)

§  Set ConvergenceLimits, Minimum System Timestep to a larger value (say, 15 minutes.  Same caution as for timestep above)

 

 

James V Dirkes II, PE, BEMP, LEED AP
www.buildingperformanceteam.com
Energy Analysis, Commissioning & Training Services
1631 Acacia Drive, Grand Rapids, MI 49504 USA
616 450 8653

 

From: EnergyPlus_Support@xxxxxxxxxxxxxxx [mailto:EnergyPlus_Support@xxxxxxxxxxxxxxx] On Behalf Of harshul
Sent: Tuesday, April 09, 2013 9:22 PM
To: EnergyPlus_Support@xxxxxxxxxxxxxxx
Subject: [EnergyPlus_Support] Energy Plus simulation run

 

 

Hi

My IDF file is 1.5 mb and it takes half an hour to run the simulation? Is there any technique to make it fast?

Thanks



__._,_.___


Primary EnergyPlus support is found at:
http://energyplus.helpserve.com or send a message to energyplus-support@xxxxxxxx

The primary EnergyPlus web site is found at:
http://www.energyplus.gov

The group web site is:
http://groups.yahoo.com/group/EnergyPlus_Support/

Attachments are currently allowed but be mindful that not everyone has a high speed connection.  Limit attachments to small files.

EnergyPlus Documentation is searchable.  Open EPlusMainMenu.pdf under the Documentation link and press the "search" button.




Your email settings: Individual Email|Traditional
Change settings via the Web (Yahoo! ID required)
Change settings via email: Switch delivery to Daily Digest | Switch to Fully Featured
Visit Your Group | Yahoo! Groups Terms of Use | Unsubscribe

__,_._,___