Does anybody know how to control the operation of series chiller operation using EnergyPlus.
Actually, I am simulating a series chiller case (say chiller on and chiller two) in EnergyPlus. I want to use chiller one cover the cooling load first. and then chiller two will cover the first. But I can to add some operation control on chiller two. For example, if the chiller two entering chilled water temperature (leaving chiller water temperature) is below certain degree, the chiller two will be turned off, otherwise it turns on.
Can I use setpoint manager to control these two chillers' operation? Thanks in advance.
Xiwang Li
--Edwin Lee, PhDEngineer, Commercial Buildings Research StaffNational Renewable Energy Laboratory