[Date Prev][Date Next][Thread Prev][Thread Next][Date Index][Thread Index]
[EnergyPlus_Support] ASHRAE 90.1 building envelope compliance methods
- To: <EnergyPlus_Support@xxxxxxxxxxxxxxx>
- Subject: [EnergyPlus_Support] ASHRAE 90.1 building envelope compliance methods
- From: <seanking.1970@xxxxxxxxxxx>
- Date: 04 Oct 2013 03:58:39 -0700
- Delivered-to: mailing list EnergyPlus_Support@xxxxxxxxxxxxxxx
- Delivery-date: Fri, 04 Oct 2013 05:01:27 -0600
- Dkim-signature: v=1; a=rsa-sha256; c=relaxed/relaxed; d=yahoogroups.com; s=echoe; t=1380884486; bh=D6xVbljhh1UtiLJ9Zqx91mr4ghFv9JisdD8uQIFvHr4=; h=Received:Received:X-Yahoo-Newman-Id:Received:X-Sender:X-Apparently-To:X-Received:X-Received:X-Received:X-Received:X-Received:X-Received:X-Received:To:Message-ID:X-Mailer:X-Originating-IP:X-eGroups-Msg-Info:X-Yahoo-Post-IP:From:X-Yahoo-Profile:X-eGroups-Approved-By:Sender:MIME-Version:Mailing-List:Delivered-To:List-Id:Precedence:List-Unsubscribe:Date:Subject:Reply-To:X-Yahoo-Newman-Property:Content-Type:Content-Transfer-Encoding; b=JU4nKVqxqpa7EzrJylf5z789fD++jE65fQbMWkBd9Qk6EGNDyVQsWPNKN3OQJBqjMZuC4W+LVq7x/HihZ4zv7vLW0xRsAwG+96NAyddz5nECLvYWLuzVvm98e4gq++ZzjEY6+I0UCxWC9+VifOIqw32cz3UCZa6g419ghQUyVJw=
- Domainkey-signature: a=rsa-sha1; q=dns; c=nofws; s=echoe; d=yahoogroups.com; b=Egb1KHsYajJ9kKy5LpkBNg4gbi056gTAQEKQpURZP4U5/hm1aS7Zu08yitXUoi90BiVDdH4zhQKFHUAQa9AceKGc399axNarK4C5wRB4Gz8xWUGY5kPGQAoa3FJyDtygLrZuEG56vhqLYx64KuH/UVY5faLaJmycEgrtIc1gQM4=;
- Envelope-to: linda@xxxxxxxxxxxxxx
- List-id: <EnergyPlus_Support.yahoogroups.com>
- List-unsubscribe: <mailto:EnergyPlus_Support-unsubscribe@yahoogroups.com>
- Mailing-list: list EnergyPlus_Support@xxxxxxxxxxxxxxx; contact EnergyPlus_Support-owner@xxxxxxxxxxxxxxx
- Reply-to: EnergyPlus_Support@xxxxxxxxxxxxxxx
- Sender: EnergyPlus_Support@xxxxxxxxxxxxxxx
Dearl all,
In ASHRAE Standard 90.1 2007 SI Edition, Page.18, it states:
5.5.3 Opaque Areas. For all opaque surfaces except doors, compliance shall be demonstrated by one of the following two methods:
1. Minimum rated R-values of insulation for the thermal resistance of the added insulation in framing cavities and continuous insulation only. Specifications listed in Normative Appendix A for each class of construction shall be used to determine compliance.
2. Maximum U-factor, C-factor, or F-factor for the entire assembly. The values for typical construction assemblies listed in Normative Appendix A shall be used to determine compliance.
My question is simple but very confused to me:
While modelling baseline buildings, there must be different U-factors between using these two options (using certain R-value from column next to U-factor column will certainly not generate the same U-factor shown in that column). Therefore EnergyPlus will generate different outputs on thermal performance (I am quite sure E+ works out heat transfer through building element using its U-factor).
So the question is: How do we know which method we should use in the model? I suppose everyone might prefer a bigger U-factor (when creating a baseline building) for whichever method being used.
Is my understanding right? I look forward to any advisable comments.
Sean
__._,_.___
Primary EnergyPlus support is found at:
http://energyplus.helpserve.com or send a message to energyplus-support@xxxxxxxx
The primary EnergyPlus web site is found at:
http://www.energyplus.gov
The group web site is:
http://groups.yahoo.com/group/EnergyPlus_Support/
Attachments are currently allowed but be mindful that not everyone has a high speed connection. Limit attachments to small files.
EnergyPlus Documentation is searchable. Open EPlusMainMenu.pdf under the Documentation link and press the "search" button.
__,_._,___