Use a detailed reporting frequency when looking at actual output.
Output:Variable,
*, !- Key Value
schedule value, !- Variable Name
Detailed, !- Reporting Frequency
schedprova; !- Schedule Name
On 1/29/2014 8:57 AM, Marco Aldegheri
wrote:
Hello,
unfortunately I have another (probably) newbie
doubt... I hope that it is one of the last... :)
I created a schedule to enable or disable the opening
program. The schedule I'm speaking about is called in
the filei"schedprova".
I don't know why but, apparently it seems to be
written in a correct form but, when I plot its value
vs time, I see that his behaviour is not like the
implemented one. I'm plotting it in timestep but i see
it moving only between 0,5 and 1... Maybe I committed
a mistake somewhere or maybe there is something that I
haven't understood yet!
Thanks, again
Marco
|
--
Richard A. Raustad
Senior Research Engineer
Florida Solar Energy Center
University of Central Florida
1679 Clearlake Road
Cocoa, FL 32922-5703
Phone: (321) 638-1454
Fax: (321) 638-1439 or 1010
Visit our web site at: http://www.fsec.ucf.edu
UCF - From Promise to Prominence: Celebrating 50 Years