[EnergyPlus_Support] ElectricLoadCenter:Storage:Battery Changing/Discharging Schedule





Hi, all

I want to control the battery charging/ discharging schedule. However, the Electricload Center: Distribution dosn't allow any user defined operation schedule.


"The basic storage control algorithm is to compare the requested
generator electricity loads to the current available supply and make up the difference with
storage. If extra power is generated, then store it. If there is a shortage, then attempt to draw
from storage to meet the remaining electricity request."



Does any know how to determine the battery operation schedule. Any clue?


Thanks very much.


Xiwang Li




__._,_.___

Posted by: xiwangli2010@xxxxxxxxx


Primary EnergyPlus support is found at:
http://energyplus.helpserve.com or send a message to energyplus-support@xxxxxxxx

The primary EnergyPlus web site is found at:
http://www.energyplus.gov

The group web site is:
http://groups.yahoo.com/group/EnergyPlus_Support/

Attachments are currently allowed but be mindful that not everyone has a high speed connection.  Limit attachments to small files.

EnergyPlus Documentation is searchable.  Open EPlusMainMenu.pdf under the Documentation link and press the "search" button.




Visit Your Group
Yahoo! Groups
PrivacyUnsubscribeTerms of Use

__,_._,___