Re: [EnergyPlus_Support] Processing multiple years in epw






One case where you need to run for more than a year is when you use closed loop ground source heat pump systems….You need to check that they are sustainable over a period of years - say 20 - 50. You just use the same weather tape repeatedly.

Regards

Robin Curtis


Robin Curtis
GeoScience Limited
 
Tel: +44 (0) 1326 211070     Fax: +44 (0) 1326 212754     Web: www.geoscience.co.uk 
Registered Office:
 Falmouth Business Park, Bickland Water Rd, Falmouth, TR11 4SZ, UK 
 
 



On 7 Nov 2014, at 11:28, Arun arynum@xxxxxxxxxxx [EnergyPlus_Support] <EnergyPlus_Support@xxxxxxxxxxxxxxx> wrote:


Hi, thank you for the post. the idea of simulating for more than a year (8760 hours) for the given energy system is really interesting. Just wondering, whether, we as a building owner/ regulator/ simulator, requires that data/ information. Typically, a year covers most weather patterns and climate changes. This leads to another prediction how to include next year weather data in .epw file given the vast uncertainties due to possible "seasonal changes" and so on... Is there any such provision in EP to include second year simulation period? 

Regards,
Arun Bhandari
eCUBE solution
Bangalore, India

Sent from my iPhone

On 07-Nov-2014, at 10:22 AM, "'jeannieboef@xxxxxxxxx' jeannieboef@xxxxxxxxx [EnergyPlus_Support]" <EnergyPlus_Support@xxxxxxxxxxxxxxx> wrote:

 

I recently accidently entered a start date "older" than the end date. E+ started with the start date, ran to the end of the year, continued flawlessly from January untill it stopped at the end date. It used a regular weatherfile.

And after my innial confussion, there came an exclamation :-)

Mit freundlichen Grüßen- Sent from my iPhone (excuse the brevity)

i. A.
Jean Marais
b.i.g. bechtold
Tel.   +49 30 6706662-23

On 06.11.2014, at 19:07, "Linda Lawrie linda@xxxxxxxxxxxxxx [EnergyPlus_Support]" <EnergyPlus_Support@xxxxxxxxxxxxxxx> wrote:

 

I cannot parse what you are saying, Ned.  I read it over twice.

There are two ways that EnergyPlus can run multiple years -- with the RunPeriod object and the repeat field.
Also we implemented something about actual year -- I can't remember if that applies to the RunPeriod, the CustomRange or both.

The CustomRange expects weather files that are hand crafted to have actual dates in the date fields and in the header (so it knows if the selection is on the weather file or not).  And they are merged together in one large file.

I can likewise send you the files I just sent Jim that implement same.

Linda

At 09:02 AM 11/6/2014, 'Edward G. Lyon' eglyon@xxxxxxx [EnergyPlus_Support] wrote:


I think what is not very clear in the documentation is if the custom weather file is the .csv file format (created from the weather generator opening a .epw or generating form some other source) or the .epw format with more than a year of data actual date order.  I suspect the latter…
 
Ned Lyon, P.E. (MA, WV)
Staff Consultant 
SIMPSON GUMPERTZ & HEGER 
781.907.9000 main
781.907.9350 direct  
617.285.2162 mobile  
781.907.9009 fax
www.sgh.com
  
From: EnergyPlus_Support@xxxxxxxxxxxxxxx [ mailto:EnergyPlus_Support@xxxxxxxxxxxxxxx
Sent: Thursday, November 06, 2014 10:49 AM
To: EnergyPlus_Support@xxxxxxxxxxxxxxx
Subject: Re: [EnergyPlus_Support] Processing multiple years in epw
 
  

Jim is right, of course - as usual.

I can send you both a file that does a custom range and a weather file.

You will need to hand create the weather file (appending the 2nd year onto the first or similar).

 I would send it to you privately.  

At 04:44 AM 11/6/2014, Jim Dirkes jim@xxxxxxxxxxxxxxxxxxxxxxxxxxx [EnergyPlus_Support] wrote:

Marko,
The purpose of the CustomRange object is for >365 day weather years, as I understand it.  I think this object became available about 2 years ago.  I was one of those who requested it so that it would be more practical to model existing buildings where the electricity and gas billing periods extended for longer than one calendar year. As it happens, I have not tested it yet, but expect to do so soon.
 
On Thu, Nov 6, 2014 at 5:38 AM, marko.ignjatovic1980@xxxxxxxxx [EnergyPlus_Support] < EnergyPlus_Support@xxxxxxxxxxxxxxx> wrote:

  
Hi all,

I have problem running simulation for two consecutive years, ie. processing raw weather data in epw. I have raw weather data starting from October 15th 2013 until October 31st 2014. Can I create extended epw containing this data period (creating epw for 8760 values is no problem)? I read I/O documentation and found that RunPeriod:CustomRange can do the trick but I am not sure. Any comment is more than welcome

Marko 



-- 

 

James V Dirkes II, PE, BEMP, LEED AP
The Building Performance Team
1631 Acacia Drive, Grand Rapids, MI 49504 
(M) 616 450 8653

The more one does what is good, the freer one becomes. There is no true freedom except in the service of what is good and just.



Content-Type: image/png; name="BPT Logo 35pct.png"
Content-Disposition: inline; filename="BPT Logo 35pct.png"
X-Attachment-Id: f_i12e40cc0








__._,_.___

Posted by: Robin Curtis <Curtis@xxxxxxxxxxxxxxxx>


Primary EnergyPlus support is found at:
http://energyplus.helpserve.com or send a message to energyplus-support@xxxxxxxx

The primary EnergyPlus web site is found at:
http://www.energyplus.gov

The group web site is:
http://groups.yahoo.com/group/EnergyPlus_Support/

Attachments are currently allowed but be mindful that not everyone has a high speed connection.  Limit attachments to small files.

EnergyPlus Documentation is searchable.  Open EPlusMainMenu.pdf under the Documentation link and press the "search" button.





__,_._,___