[Equest-users] Workflow question - What is the best way to model the baseline case and then design case? LEED
James Geers
jgeers at sfa-architects.com
Mon Dec 15 08:07:29 PST 2008
I am modeling a building that has a Packaged VAV system as the base case and
a standard VAV system as the design case. Is there any easy way to set up a
second mechanical system and then reassign the zones to it as a parametric
run? I'm trying to avoid creating a second model so that I can keep any
adjustments to the schedule, loads or envelope identical. I have
investigated setting up dummy zones to assign the VAV mechanical system to,
but I can't figure out how to reassign the zones as a parametric run. Thank
you.
James F. Geers
Registered Architect
LEED Accredited Professional
SFA Architects
300 West Fourth Street
Cincinnati, Ohio 45202
513.721.0600
513.721.0611 (fax)
-------------- next part --------------