[Equest-users] Workflow question - What is the best way to model the baseline case and then design case? LEED

James Geers jgeers at sfa-architects.com
Mon Dec 15 08:07:29 PST 2008


I am modeling a building that has a Packaged VAV system as the base case and
a standard VAV system as the design case.  Is there any easy way to set up a
second mechanical system and then reassign the zones to it as a parametric
run?  I'm trying to avoid creating a second model so that I can keep any
adjustments to the schedule, loads or envelope identical.  I have
investigated setting up dummy zones to assign the VAV mechanical system to,
but I can't figure out how to reassign the zones as a parametric run.  Thank
you.

 

James F. Geers

Registered Architect

LEED Accredited Professional

 

SFA Architects

300 West Fourth Street

Cincinnati, Ohio 45202

513.721.0600    

513.721.0611 (fax)

 

-------------- next part --------------
An HTML attachment was scrubbed...
URL: <http://lists.onebuilding.org/pipermail/equest-users-onebuilding.org/attachments/20081215/0be5e5a3/attachment.htm>


More information about the Equest-users mailing list