[Equest-users] Manufacturing Building Energy Simulation- eQuest
Ramana Koti
ramana.koti at gmail.com
Thu May 21 06:33:00 PDT 2009
If you look up Credit Interpretation Requests on EA Cr1, you'll see
that an alternate compliance path can be proposed that's specific to
your manufacturing facility, especially for end uses not regulated by
Ashrae 90.1.
You'd probably still have to include all end uses.
Ramana.
On May 21, 2009, at 4:39 AM, cic at jci.com wrote:
>
> Dear All,
>
> Refer the following data.
>
> A manufacturing building has the following area
>
> Common area,office
> area =
> 22% of the building area which contribute 13% of a/c requirement
> Manufacturing area (clean room+
> +) = 57% of the building area
> which contribute 87% of a/c requirement
> Un air-conditioned
> area
> = 21% of the building area.
>
> Now this building needs LEED Certification.
>
> To achieve EA Credit1, whether the clean room load(process) needs
> to be considered in baseline design during modelling? or only we
> need to consider the common area+office area+Unconditioned area.
>
> Advance thanks for your valuable feedback.
>
> Thanks and regards
> Kathiresan
>
>
> _______________________________________________
> Equest-users mailing list
> http://lists.onebuilding.org/listinfo.cgi/equest-users-onebuilding.org
> To unsubscribe from this mailing list send a blank message to EQUEST-USERS-UNSUBSCRIBE at ONEBUILDING.ORG
-------------- next part --------------
An HTML attachment was scrubbed...
URL: <http://lists.onebuilding.org/pipermail/equest-users-onebuilding.org/attachments/20090521/975ce865/attachment-0001.htm>
More information about the Equest-users
mailing list