[Equest-users] Total Run Hours
Jansen, Connor
Connor.Jansen at wspfk.com
Thu Aug 19 10:57:07 PDT 2010
Hello All,
Quick question for you. How are the total run hours summated in the SS-R
reports? I have two models baseline and proposed with the same fan
schedules however the run hours are different. I was under the
impression that the run hours are directly related to the times in which
the fans are scheduled off/on. Perhaps this is still the case and
something else has been altered between my runs. Thank you for the
clarification.
Regards,
Connor