[Equest-users] Total Run Hours

Jansen, Connor Connor.Jansen at wspfk.com
Thu Aug 19 10:57:07 PDT 2010


 

Hello All,

 

Quick question for you. How are the total run hours summated in the SS-R
reports? I have two models baseline and proposed with the same fan
schedules however the run hours are different. I was under the
impression that the run hours are directly related to the times in which
the fans are scheduled off/on. Perhaps this is still the case and
something else has been altered between my runs. Thank you for the
clarification. 

 

Regards,

 

Connor

-------------- next part --------------
An HTML attachment was scrubbed...
URL: <http://lists.onebuilding.org/pipermail/equest-users-onebuilding.org/attachments/20100819/2ef917b6/attachment.htm>


More information about the Equest-users mailing list