Anna:
If you shut off equipment, turn off lights, or reduce people, your heating will have to work harder.
Not sure what "significant" means.
John R. Aulbach, PE, CEM
Senior Energy Engineer
________________________________
PartnerEnergy
1990 E. Grand Avenue, El Segundo, CA 90245
W: 888-826-1216, X254| D: 310-765-7295 | F: 310-817-2745
www.ptrenergy.com| jaulbach at ptrenergy.com
________________________________
From: Anna Kim <Anna.Kim at cadmusgroup.com>
To: "equest-users at lists.onebuilding.org" <equest-users at lists.onebuilding.org>
Sent: Tue, June 15, 2010 12:21:16 PM
Subject: [Equest-users] Heating load during weekends
Hello,
I have been using EQuest to run some commercial building simulations. I’ve found that the electric (DX) heating load during weekends in the wintertime are unusually high compared to weekday loads. I ran a building that was a hospital with 24/7 occupancy and yet the heating loads between weekend and weekday are significantly different.
Was there some hard- or soft-coded adjustment made in the program for weekends?
Thanks,
Anna Kim, Analyst
The Cadmus Group, Inc.
720 SW Washington Street
Suite 400
Portland, OR 97205
Voice: (503) 575-4556
Main: (503) 467-7100
Cell: (503) 406-8008
Fax: (503) 575-4656
-------------- next part --------------
An HTML attachment was scrubbed...
URL: <http://lists.onebuilding.org/pipermail/equest-users-onebuilding.org/attachments/20100615/f6b1e91d/attachment-0001.htm>
More information about the Equest-users
mailing list