[Equest-users] Supply T too low
Bill Lafley
bill.lafley at cetonline.org
Tue Aug 2 13:49:15 PDT 2011
Hello,
Has anyone gotten the warning below? Is there a fix for it?
**WARNING**********************************************************************
PREHEAT/HEATING-CAPACITY in SYSTEM EL2 Sys2 (UVT) (G.N5)
is too low to provide the requested supply temperature for
the calculated mixed air temperature using total ZONE loads
(on LS-A/B) and SYSTEM design parameters, plus outside air
conditions (on LS-C), and specified capacities & air flows.
Requested temperature is 120.00 calculated is 72.00
Check HEATING-CAPACITY, HEAT-SET-T, PRE-HEAT-T, MAX-SUPPLY-T,
DESIGN-HEAT-T, and ZONE loads for consistency.
Thanks,
Bill
--
<http://www.cetonline.org>
Bill Lafley <mailto:blafley at cetonline.org> | Energy Analyst
Center for EcoTechnology | 320 Riverside Drive - 1A | Florence MA 01062
413-586-7350 ext. 222 | 413-695-2730 (cell)
<http://www.cetonline.org>www.cetonline.org
<http://www.cetonline.org/Mailist/VR_Signup.php>
More information about the Equest-users
mailing list