[Equest-users] Excessive Heat Recovery Chiller Operation
Anthony Hardman
Anthony at GreenEngineer.com
Tue Aug 30 08:05:22 PDT 2011
Couldn't find an answer in the archives so I thought I'd solicit the
experts.
Objective: I only want my HRC to recover waste heat when there's a call for
cooling.
Problem: I have more chiller operation in the winter than the summer. It
seems my HRC's are activating whenever there is a demand on the hot water
loop it's attached to.
Question: Does one have to specify equipment controls to get the HRC to
operate in the desired mode? If not, what else am I doing wrong here?
Anthony Hardman, PE
LEED AP BD&C
Building Performance Analyst
The Green Engineer, LLP
Sustainable Design Consulting
50 Beharrell St
Concord, MA 01742
O: 978/610-2801
C: 720/840-7862
-------------- next part --------------
An HTML attachment was scrubbed...
URL: <http://lists.onebuilding.org/pipermail/equest-users-onebuilding.org/attachments/20110830/aa8ebbf3/attachment.htm>
More information about the Equest-users
mailing list