[Equest-users] Unmet Hours: Heating
John Aulbach
jra_sac at yahoo.com
Tue Nov 29 08:38:07 PST 2011
The "when" of the unmet heating hours would help. Startup? Cold months only? You have a reheat system (with your VAV). Try making the deadband larger.
John R. Aulbach, PE, CEM
Senior Energy Engineer
________________________________
PartnerEnergy
1990 E. Grand Avenue, El Segundo, CA 90245
W: 888-826-1216, X254| D: 310-765-7295 | F: 310-817-2745
www.ptrenergy.com| jaulbach at ptrenergy.com
________________________________
From: "Akshay.Pahade at jci.com" <Akshay.Pahade at jci.com>
To: equest-users at lists.onebuilding.org
Sent: Tuesday, November 29, 2011 2:31 AM
Subject: [Equest-users] Unmet Hours: Heating
Hello All,
We are trying to model an office campus of around 12 buildings. The chiller plant has around 10 chillers and boiler plant has around 4 nos. of steam boilers.
On the air side, the systems are a combination of VAV systems and FCUs ( modeled as SZRH in eQuest)
After adding all the possible inputs, we are not able to meet the unmet hours, mostly in heating. Any hints???
Regards,
Akshay Pahade
Energy Solutions,
CoEE, Johnson Controls,
Mumbai, India.
_______________________________________________
Equest-users mailing list
http://lists.onebuilding.org/listinfo.cgi/equest-users-onebuilding.org
To unsubscribe from this mailing list send a blank message to EQUEST-USERS-UNSUBSCRIBE at ONEBUILDING.ORG
-------------- next part --------------
An HTML attachment was scrubbed...
URL: <http://lists.onebuilding.org/pipermail/equest-users-onebuilding.org/attachments/20111129/ff59bfa3/attachment-0002.htm>
More information about the Equest-users
mailing list