[Equest-users] Baseline to Proposed comparison in equest

Arpan Bakshi arpanbakshi at gmail.com
Tue Aug 14 10:15:20 PDT 2012


Nimesh it looks like you are on the front end of your performance rating
method journey.
A good place to begin would be the IBPSA Building Energy Modeling
Workshops. (downloadable .pptx)

http://www.bembook.ibpsa.us/index.php?title=Downloads




*Arpan Bakshi**    *LEED AP BD+C, ESTIDAMA PQP



On Tue, Aug 14, 2012 at 1:07 PM, Nimesh Prajapati Nimesh <
nimonomics at yahoo.in> wrote:

> Dear All,
>
> I am using following methodology for Baseline to Proposed comparison in
> equest:
>
> 1. First using eQuset creating Baseline model with the help of Appendix -
> G.
> 2. And then creating Proposed model by saving the baseline model and
> changing it with Proposed model data.
> 2. Then taking all the baseline model and Proposed model data in separate
> spreadsheet and comparing it.
>
> Is it correct? Or I need to do something else?
>
> Can I create Baseline and Proposed model in the same eQuest file and have
> comparison?
>
> If somebody have answer please let us know. . . .
>
> Thanks,
>
> Nimesh Prajapati
>
>
> (+91 9687133492)
> HVAC Design Engineer
>
> _______________________________________________
> Equest-users mailing list
> http://lists.onebuilding.org/listinfo.cgi/equest-users-onebuilding.org
> To unsubscribe from this mailing list send  a blank message to
> EQUEST-USERS-UNSUBSCRIBE at ONEBUILDING.ORG
>
>
-------------- next part --------------
An HTML attachment was scrubbed...
URL: <http://lists.onebuilding.org/pipermail/equest-users-onebuilding.org/attachments/20120814/0181d1b6/attachment-0002.htm>