Check p. 954 in the IO Reference: That report variable is keyed to the "People" object (occupancy) only when you use the variable "...Setpoint Not Met While Occupied", and it looks for instances where the room temp varies from the setpoint by more than .2C.
If you don't use the ".. While Occupied" version of the report variable, occupancy is not checked.
--- In EnergyPlus_Support@xxxxxxxxxxxxxxx, "Bing Dong" <bingcat2007@...> wrote: > > Hi, > > Regarding to the Report Variable: Time Not Met Comfortable, does it > dynamically links back to the occupancy schedule I specified, such as > excluding the weekend for office building? I found even I got 0 hour > for Time Not Met Setpoint (23 C), there is still 8 hours/week that not > met comfortable. > > Thanks, > > Bing >