[EnergyPlus_Support] Calculation of U-value
- To: EnergyPlus_Support@xxxxxxxxxxxxxxx
- Subject: [EnergyPlus_Support] Calculation of U-value
- From: "billysonny1" <bscr_14@xxxxxxxxxxx>
- Date: Wed, 26 Jun 2013 23:05:13 -0000
- Delivered-to: mailing list EnergyPlus_Support@xxxxxxxxxxxxxxx
- Delivery-date: Wed, 26 Jun 2013 17:05:17 -0600
- Dkim-signature: v=1; a=rsa-sha256; c=relaxed/relaxed; d=yahoogroups.com; s=echoe; t=1372287916; bh=AuS3MR4AfH11LTBhhjGzZP5gmSkY8uuKDZ2zwigVsUU=; h=Received:Received:X-Yahoo-Newman-Id:X-Sender:X-Apparently-To:X-Received:X-Received:X-Received:X-Received:X-Received:To:Message-ID:User-Agent:X-Mailer:X-Originating-IP:X-eGroups-Msg-Info:X-Yahoo-Post-IP:From:X-Yahoo-Profile:Sender:MIME-Version:Mailing-List:Delivered-To:List-Id:Precedence:List-Unsubscribe:Date:Subject:Reply-To:X-Yahoo-Newman-Property:Content-Type:Content-Transfer-Encoding; b=UPoNpY0KBaiepKPM/7QCVA2sNV1ou62bJ4hpBaOAwnVFASsfolx8KK0oNvyYOEZvr3wgiaZjdv9kDkZWWsoeD4TiBJCJaJ/gN0ShtFmpF4RLl67t3ZXgeBtOlPoCUhpyqgZ18tkMU1YuCfZ0VCdnFbBWQw5YpACV2wwqQVd9RR4=
- Domainkey-signature: a=rsa-sha1; q=dns; c=nofws; s=echoe; d=yahoogroups.com; b=euHn018ngiZSsu+Ej37qRUCxGYEOi1/FLEm3T24YYJu8H5cFNbmXGfTxiVA41ACidwgadOMsjIDxvMbFOzew/fVmgtSeqGHhNYPSVS/ZHf4s5zaJlAkkZD9DCjJbTf7X3g1ROhfwrHZUWN+EGmu/jbRYvfeLdDfW+SRcJ/qY7sc=;
- Envelope-to: linda@xxxxxxxxxxxxxx
- List-id: <EnergyPlus_Support.yahoogroups.com>
- List-unsubscribe: <mailto:EnergyPlus_Support-unsubscribe@yahoogroups.com>
- Mailing-list: list EnergyPlus_Support@xxxxxxxxxxxxxxx; contact EnergyPlus_Support-owner@xxxxxxxxxxxxxxx
- Reply-to: EnergyPlus_Support@xxxxxxxxxxxxxxx
- Sender: EnergyPlus_Support@xxxxxxxxxxxxxxx
- User-agent: eGroups-EW/0.82
Hello everyone,
I'm in the process of filling out the table 1.4 for LEED EAp2 submission, my question is about this ''How were the Proposed case framed assembly fenestration U-factors determined?'' along with the following options:
* NFRC testing for site-assembled fenestration
* NFRC testing for manufactured fenestration assemblies
* Table A8.2 (windows) and Table A8.1 (skylights)
* LBNL Window 5 or Window 6 calculations
* Energy simulation includes separate frame and glazing
Normally the U-value I have for the projects I'm working on, doesn't include framing, just the glazing (please confirm if this always happen in the technical sheet of the glazing).
Please help me figure out the meaning of the previos options and give me a big picture about how different would be considering the framing in relation to not considering it.
Thanks in advance.
Billy.
------------------------------------
Primary EnergyPlus support is found at:
http://energyplus.helpserve.com or send a message to energyplus-support@xxxxxxxx
The primary EnergyPlus web site is found at:
http://www.energyplus.gov
The group web site is:
http://groups.yahoo.com/group/EnergyPlus_Support/
Attachments are currently allowed but be mindful that not everyone has a high speed connection. Limit attachments to small files.
EnergyPlus Documentation is searchable. Open EPlusMainMenu.pdf under the Documentation link and press the "search" button.
Yahoo! Groups Links
<*> To visit your group on the web, go to:
http://groups.yahoo.com/group/EnergyPlus_Support/
<*> Your email settings:
Individual Email | Traditional
<*> To change settings online go to:
http://groups.yahoo.com/group/EnergyPlus_Support/join
(Yahoo! ID required)
<*> To change settings via email:
EnergyPlus_Support-digest@xxxxxxxxxxxxxxx
EnergyPlus_Support-fullfeatured@xxxxxxxxxxxxxxx
<*> To unsubscribe from this group, send an email to:
EnergyPlus_Support-unsubscribe@xxxxxxxxxxxxxxx
<*> Your use of Yahoo! Groups is subject to:
http://docs.yahoo.com/info/terms/