Thanks, Jean.
Sorry, but my original post was sent in hurry.
Here I want to reassure that:
Baseline building envelope uses ONLY:
Proposed building can use ANY:
shown in Tables 5.5-1 through 5.5-8, with typical detailed constructions listed in appendix A (or recommend proposed building using these constructions even though the use of constructions for proposed design can be arbitrary, as the Standard states "All components of the building envelope in the proposed design shall be modeled as shown on architectural drawings or as built for existing building envelopes.").
Please confirm above understanding is right. If not, please correct with comments. Thank you very much indeed.
Sean
On 08.10.2013, at 18:02, <seanking.1970@...> wrote:
Dear all,
In Standard 90.1-2007 SI edition, Page 178, Table G3.1 No.5 Building Envelope section:Can I understand for baseline building we only need to use roof - insulation entirely above deck, above-grade wall - steel-framed, floor - steel-joisted etc. Other constructions in Appendix A just for the purpose of using for proposed building?Thanks and regards,Sean