Check your spelling: Throught?
Â
  Through:07/15,          !- Field 5
   For: Weekdays,          !- Field 6
   Until: 7:30,            !- Field 7
   0,                      !- Field 8
   Until: 11:30,           !- Field 9
   1,                      !- Field 10
   Until: 13:00,           !- Field 11
   0,                      !- Field 12
   Until: 17:30,           !- Field 13
   1,                      !- Field 14
   Until: 24:00,           !- Field 15
   0,                      !- Field 16
   For: AllOtherdays,      !- Field 17
   Until: 24:00,           !- Field 18
   0,                      !- Field 19
   Through:08/01,          !- Field 20
   For: alldays,           !- Field 21
   Until: 24:00,           !- Field 22
   0,                      !- Field 23
   Throught: 12/20,        !- Field 24
   For: weekdays,          !- Field 25
   Until: 7:00,            !- Field 26
   0,                      !- Field 27
   Until: 11:30,           !- Field 28
  Â
Â
Ned Lyon, P.E. (MA, WV)
Staff ConsultantSIMPSON GUMPERTZ & HEGER
781.907.9000Â main
781.907.9350 directÂ
617.285.2162 mobileÂ
781.907.9009Â fax
www.sgh.com
Send FilesFrom: EnergyPlus_Support@
yahoogroups.com <EnergyPlus_Support@yahoogroups.com >
Sent: Monday, July 9, 2018 3:13 PM
To: EnergyPlus_Support@yahoogroups.com
Subject: [EnergyPlus_Support] Schedule compact - errors [1 Attachment]Â
Â
Hello.
Â
I keep getting these severe errors:
Â
 ** Severe ** ProcessScheduleInput: Schedule:Compact="OCUP_SALAS" has overlapping days in its schedule pointers
  ** Severe ** ProcessScheduleInput: Schedule:Compact="OCUP_SALAS BER?" has overlapping days in its schedule pointers
  ** Severe ** ProcessScheduleInput: Schedule:Compact="OCUP_VARS" has overlapping days in its schedule pointers
  ** Severe ** ProcessScheduleInput: Schedule:Compact="OCUP_AUD" has overlapping days in its schedule pointers
  ** Severe ** ProcessScheduleInput: Schedule:Compact="OCUP_SERV_
COZ" has overlapping days in its schedule pointers   ** Severe ** ProcessScheduleInput: Schedule:Compact="OCUP_SERV_
PROF" has overlapping days in its schedule pointers Â
I looked it up a hundred times and I coudn't fix the error. I would appreciate if someone could give it a look.
Â
Thank you !!
Â
--
Thais Gonçalves Sartori
(27) 99903 4665
Arquiteta - A66010-8
Mestre em Engenharia Civil
Â
CurrÃculo Lattes: http://lattes.cnpq.br/
8848943203048272 Linkedin: www.linkedin.com/in/thais-
sartori-a4695937 Â
Â
Â
Â
Â
--Thais Gonçalves Sartori(27) 99903 4665Arquiteta - A66010-8Mestre em Engenharia CivilCurrÃculo Lattes: http://lattes.cnpq.br/8848943203048272
__._,_.___